New Mexico: I-10 Construction Near Mesquite Now Set for January Completion

I-95 Richmond | Virginia DOTA lengthy construction project along a segment of Interstate 10 in southern Doña Ana County is nearing completion, bringing relief to thousands of area drivers.

Later this week, the eastbound on-ramp and off-ramp for Exit 151 near Mesquite will reopen, New Mexico Department of Transportation spokeswoman Bridgette Spedalieri said.

But the bridge and westbound on- and off-ramps there, about halfway between Las Cruces and El Paso, may stay closed, she added, till early January due to delays caused by weather and unexpectedly stubborn soil.

read the full story…